§ 4116.07. Duties of the city.  


Latest version.
  • City review of applicant plats, plans, and permits shall occur after date of acceptance in accordance with the following timeframes ("days" are defined as city business days):

    Process Service Standard
    Platting—Preliminary plat 22 days
    Platting—Final plat 42 days
    One-, two-, three-family residential permit Seven days
    Interior remodel/tenant finish Eight days
    Commercial plan approval/permit 20 days
    Engineering plan approval 25 days

     

(Ord. 2178-01 § 2 (part).)